"শেখ হাসিনার উদ্যোগ, ঘরে ঘরে বিদ্যুৎ"

<<< Generation at Maximum Demand total of Previous Day 875 MW " >>>
Ongoing Projects Gallery

Summary
Project Times
Project Status




Project Highlights:  

Name of the Bid: Construction of Ashuganj 450 MW Combined Cycle Power Plant (North) on Turnkey Basis
Bidding Procedure: Two stage bidding (ADB)
Net Output: 450?20% MW
CCGT Configuration: Single Shaft or Multi shaft (not more than 2:2:1 for Multi Shaft)
Completion Period: CCGT- 30 months from contract effective date
Plant Life: 25 years

Objective:  

a. To narrow the ever increasing gap between demand and supply of electricity through gas based low-cost generation in the north-east zone of the country.
b. To meet up increasing power demand in the country by adding local generation.
c. To increase the power generation through utilization of countrys natural gas resources available nearest to the proposed power plant site with requisite pressure.
d. To accelerate the economic development of the country by adequate and reliable power generation and to support the planned target of power demand.
e. To overcome the present generation shortage by increasing generation and to minimize load shedding.
f. To enhance the stability and reliability of the national grid system and reduce the transmission loss by local generation.
g. To increase energy efficiency of power generation.

Estimated cost of the project :  Estimated (Lakh Taka): Total : 340,002.50 (Local/GOB : 35,271.65; F.Ex./PA :299,604.60; APSCL: 5,126.25)