"শেখ হাসিনার উদ্যোগ, ঘরে ঘরে বিদ্যুৎ"

Ongoing Projects

1. Ashuganj 100 MW HFO Based Power Plant
Project Financed   : APSCL Own Fund
Project Duration   : 10 Months
Project Highlights:  

Gross Output: 95-115 MW
Net Output: -
CCGT Configuration: N/A
Completion Period: 10 Months
Plant Life: 15 years

Objective:  

a.       To meet up increasing power demand in the country by adding local generation.

b.      To accelerate the economic development of the country by adequate and reliable power generation and to support the planned target of power demand.

c.       To enhance the stability and reliability of the national grid system and reduce the transmission loss by local generation.

d.      To increase energy efficiency of power generation.

Estimated cost of the project :  -
Date of ICB floating:  November 25, 2017
Date of tender opening:  January 22, 2018
Notification of Award (NOA):  -
Notification of Award (NOA):   -
Acceptance of NOA:   -
Contract Agreement:  -
Contractor:  TBD (To Be Determind)
Commencement of early works:  TBD
Date of LC opening:  TBD
Date of commencement:  TBD
Date of completion:  Dec, 2018
Commercial Operation Date:  Dec, 2018
Project Director:  Md. Kamruzzaman Bhuiyan
Physical Progress :  

-

Financial Progress:  

-

2. Land Acquisition, Land Development and Protection for Patuakhali 2x660 MW Ultra-Super Critical Coal Fired Power Plant Project.
Project Highlights:  
Objective:  
Estimated cost of the project :  
Date of ICB floating:  -
Date of tender opening:  -
Notification of Award (NOA):  -
Notification of Award (NOA):   -
Acceptance of NOA:   -
Contract Agreement:  -
Contractor:  
Commencement of early works:  
Date of LC opening:  
Date of commencement:  
Date of completion:  
Commercial Operation Date:  
Project Director:  
Physical Progress :  
  • Proposal for 930.615 acres of Land Acquisition in Mouza based has been submitted to DC Office, Patuakhali.
  • Proposal for 289 acres of Land Acquisition in Debpur Mouza has been submitted to Ministry of Land.
  • DPP has been submitted to Industries and Energy Division, Ministry of Planning.
  • MOU has been signed between APSCL and China Energy Engineering Corporation Limited (Energy China) on 13 July 2017.
Financial Progress:  
3. Ashuganj 400MW CCPP (East) Project
Project Financed   : ADB >107.57 m USD, IDB:220.00 m USD
Project Duration   : 60 Months
Project Highlights:  

Gross Output: 389.40 MW
Net Output: 380.68 MW
CCGT Configuration: Single Shaft
Completion Period: 38 Months
Plant Life: 25 years

Objective:  

a. To narrow the ever increasing gap between demand and supply of electricity through gas based low-cost generation in the north-east zone of the

b. To meet up increasing power demand in the country by adding local generation.

c. To increase the power generation through utilization of country's natural gas country resources available nearest to the proposed power plant site with requisite pressure.

d. To accelerate the economic development of the country by adequate and reliable power generation and to support the planned target of power demand.

e. To overcome the present generation shortage by increasing generation and to minimize load shedding.

f.  To enhance the stability and reliability of the national grid system and reduce the transmission loss by local generation.

g. To increase energy efficiency of power generation.

Estimated cost of the project :  Total: 293,136.39, GOB: 42,0868.53,PA: 235,828.02, APSCL: 15,239.84
Date of ICB floating:  -
Date of tender opening:  -
Notification of Award (NOA):  -
Notification of Award (NOA):   -
Acceptance of NOA:   -
Contract Agreement:  -
Contractor:  
Commencement of early works:  
Date of LC opening:  
Date of commencement:  
Date of completion:  June, 2020
Commercial Operation Date:  
Project Director:  Engr. Kshitish Chandra Biswas
Physical Progress :  

International Tender Notice (1st Stage) published in international newspaper on 12th May 2016 for the selection of EPC contractor.

Contract signed with M/S Poyry Switzerland Ltd, Switzerland & Atlanta Enterprise Limited, Bangladesh for Project Implementation Consultancy Service on last 29th March 2017.

Invitation for Second Stage Bids was issued on 15th October 2017 to the short listed bidders. 

Financial Progress:  

0.077%

Downloads

Foreign Tour/Training

Information Memorandum_ Ashuganj Power Station Company Limited's non convertible, fully reedemable coupon bearing bond

Integrity

Land Acquisition, Land Development and Protection for Patuakhali 1320 MW Super Thermal Power Plant project.

100 MW Grid Tied Solar Park Project

Ashuganj 400MW CCPP (East) Project

NOC

Training Program

Easy Utility Service

Dual Fuel Based CCPP

North-Bengal Coal Fired Thermal Power Plant

Achievement of Present Government in Power Sector.

APSCL Power Generation Master Plan


Notice

! Notice not available...